Land of Iron Consultation – 12 December 2017

Land of Iron Update – Breakthrough!

A group of local volunteers, armed with buckets and spades on Saturday 28 October, dug down through the mud and discovered the original upstream entrance to the Reeking Gill culvert, with Shaun Doughty having used a digger to clear the site (see previous update on 4 October). Work will now continue to shift the rest of the debris from the entrance and expose more of the large stone archway. Muscle power and determination won the day and well done to all.

The entrance exposed at last!

Work has also been done to clear some of the smaller culverts along the old railway line so that water no longer builds up and threatens the integrity of the track bed.

A cleared culvert near Nab Scar

A fuller progress report will be given around the New Year, so that all can see how this marvellous project is progressing. Meanwhile please look at the NYMNPA call for volunteers poster and join in.

 

Land of Iron Project Update – 4 October 2017

Work on the Land Of Iron project continues apace in Rosedale. The repair done to the track at Stone Kilns is greening up nicely and will be barely visible from a distance by this time next year:

Trackway repair as at 4 October 2017

New, bigger interpretation boards have been placed at the three kiln sites:

Stone Kilns Board

Work is currently ongoing to clear the upsteam entrance to the major culvert under Reeking Gill to prevent the dangerous build up of water behind the embankment:

Shaun Dougherty at work

Save Rosedale Abbey Church Appeal – 2018 Calendar

As part of the appeal to raise funds to save St Mary and St Lawrence Church in Rosedale Abbey, a 2018 calendar has been produced which will be on sale at Rosedale Show on 19 August in the Rosedale History Society tent on Row F and also in the Church Tea Tent by the entrance to the main ring, for £10 a copy with envelope.

A high quality, full colour calendar showing scenes of Rosedale throughout the year.

The calendar is a lovely reminder of Rosedale and will make an ideal Christmas present, so please make an effort to buy at least one to help us raise the funds for the urgent  repairs needed to the church.

The calendar will also be on sale at the church repair appeal coffee morning at the Coach House Inn on Saturday 2 September  between 10.00 and 12.00 am – please make a note of the time and date for your diaries.

Invitation – Andy Goldsworthy – Hanging Stones Project

The David Ross Foundation invites you to Westerdale Village Hall for a public talk by internationally renowned artist Andy Goldsworthy.  

A chance to hear the artist speak about his wider practice and his ‘Hanging Stones’ project in Northdale Valley, North Yorkshire Moors.

Thursday 6th July 2017

6.30pm

Westerdale Village Hall, Whitby YO21 2DT

All welcome, seating available on a first come first served basis

The Tree House
The Burnt Tree
The Ochre or Okker Wall

Land of Iron Update

The repair to the trackway at the stone kilns at East Mines is maturing nicely with the grass that was seeded in the sandbags now sprouting well.

Grass sprouting from the sandbags in the gabions

Land of Iron – This Exploited Land

New Name and Logo

land-of-iron-rosedale

TEL East Mines Update at 10 December 2016

The site has now been cleared and most of it restored, although the track way still needs to be surfaced, it is hoped, with furnace cinder to replicate its orginal state.

The shoring-up is now complete.
The shoring-up is now complete.
The approach to the site.
The approach to the site.
The works base area.
The works base area.

TEL East Mines Update 10 as at 26 November 2016

Not much progress to report as the recent wet weather has prevented work on the site. Some restoration of the approaches to the kilns area is needed and the immediate area of the workings needs tidying up.tel-east-mines-update-26-nov-16-2 tel-east-mines-update-26-nov-16-3

TEL East Mines Update 16 November 2016

All the main work is now completed and the portakabins and plant have been removed from the area as of today. All that remains is to restore the approaches to the work site by the kilns and top dress the new pathway. The next phase will be to clear the culverts at Reeking Gill to prevent further erosion there.tel-east-mines-update-9-1-16-nov-16 tel-east-mines-update-9-2-16-nov-16 tel-east-mines-update-9-3-16-nov-16